The Lumos & Associates engineering firm is working on the improvement plans for this project. We have met with the Kingslane HOA and discussed and coordinated the plans for the new wall along the highway. NV Energy plans are complete for a new meter and street lighting.
Kingslane Sidewalk
Highway 395 Crosswalk Upgrades
On 11/2/15, Lumos was awarded the engineering/surveying/materials testing and construction phase services. A study was needed for NDOT to review the viewshed corridor. The Hwy 395 Crosswalk Upgrades were put out to bid on April 17, 2020.
Bid Opening
On May 5, 2020 at the Gardnerville Town Board Meeting, the Board rejected all bids.
Hellwinkel Shop
TSK Architects is working on plans for the Hellwinkel Shop. They will be providing construction and demolition drawings, structural and electrical designs. When the project goes to construction Lumos & Associates will be providing testing and inspection.